Posted on: October 2, 2020

[ARCHIVED] Update: Watermain Extension for Selous Creek

Over the next couple of weeks, the Kays Contracting crews will continue to work toward Mountain Station reservoir along the Hoover Street Right-of-Way. Other than the immediate residents,  little disruption is anticipated.  The works on Hoover Street below the Great Northern Trail are mostly complete and plan to be re-surfaced after the Thanksgiving weekend.

The Hil-Tech Contracting crews have mobilized to site and set up a site office. They have completed the shallow utility install for electrical and controls systems and plan to start placing concrete for the controls' structure by the end of next week.

The contractors do not foresee the need for any detours or closures of trails nor roads over the next week. However, the area around the Mountain Station reservoir will be a busy place as two contractor crews marshal at the site. Please be mindful of the construction zones, traffic control personnel and all construction signage.

 

Hoover Street ROW below the Mountain Station reservoir, looking West. The Kays Contracting crew is working from the Great Northern Trail uphill along the ROW toward the reservoir.

 Hoover trench

Mountain Station facility and the grant signage attached to the perimeter fence.

 grant signage

Looking East, uphill past the facility to the Hil-Tech Contracting site office.

hiltech office