News Flash

City Project Gallery

Posted on: November 24, 2023

Pier Project Update - November 24, 2023

2023-11-17 - Canopy 2

As we head into December, work on the Pier project is continuing with the last few days bringing us blue skies. 

2023-10-20 - Ladybird Enclosure

Ladybird display building, looking to the north west.


2023-10-20 - Ladybird Enclosure 2

Ladybird display building, looking to the north east.


2023-11-10 - Ladybird Enclosure Inside out view of the Ladybird display building.


2023-11-10 - Canopy Steel 4Canopy steel construction – anchoring the four corners.

2023-11-10 - Canopy Steel 5The Canopy structure is a unique shape.

2023-11-17 - Canopy 3A sunny day on the site, looking south west from the Pier.

2023-11-17 - Canopy 2This picture offers a perspective of the canopy size.

2023-11-10 - Floating DocksSwim docks at the Pier are complete.

  Work being completed currently:

  • North Mountain installed temporary deck protection and prepared site for steel erection. 
  • MarTech Motor Winding to fabricate and erect canopy steel structure. Steel to be shipped for galvanizing. Steel erection starting tentatively on November 8th.
  • Works by City of Nelson, Tru Mechanical and DHC Communications on the Ladybird display. building to install security controls, controls and balance the enclosure systems.
  • MarTech Motor Winding erecting canopy steel. 
  • MarTech Electric installing Ladybird ceiling LED fixtures.
  • MarTech Electric hooked up and tested pier handrail lighting. 
  • North Mountain preparing for canopy wood cladding installation – arranging material orders. 
  • North Mountain installing steel transition ramps to floating dock gangway ramps.

Contractors on site:

North Mountain Construction, MarTech Electric, MarTech Motor Winding, City of Nelson Staff, DHC Communications and Tru Mechanical