News Flash

Posted on: June 19, 2020

UPDATE: Watermain Extension for Selous Creek

2020 1

Kays Road Contracting Ltd., continued with the install of watermain on the Great Northern Trail this past week, currently positioned to enter the Mountain Station parking lot from the south. They’ve made good progress and completed the install o...

Read on...

City Project Gallery
Posted on: June 12, 2020

UPDATE: Watermain Extension for Selous Creek

June 12 Update 1

Progress on installation of the watermain on the Great Northern Trail (GNT) slowed considerably at times over the past couple weeks due to rock. However, the past few days have been clear of rock and Kays Road Contracting Ltd., has made good progress rece...

Read on...

City Project Gallery
Posted on: June 5, 2020

Paving Project at Intersection of Vernon & Josephine Streets

PublicNotice_PublicWorks

PAVING PROJECT AT INTERSECTION VERNON & JOSEPHINE STREET
On Monday, June 8th  & Tuesday, June 9th 2020, crews will be milling off existing road surface and overlaying with new pavement between 7:00am to 5:00pm.
Expect periodic road closures...
Read on...

City Project Gallery
Posted on: June 5, 2020

UPDATE: Watermain Extension for Selous Creek

IMG_0403

The prime contractor for the construction of the Selous Creek Watermain Extension, Kays Road Contracting Ltd., has made good progress this week, moving northward along the Great Northern Nelson-Salmo Trail (GNT) toward the Mountain Station parking lot. Ov...

Read on...

City Project Gallery
Posted on: May 29, 2020

Watermain Construction: Great Northern Trail Nelson-Salmo

2

Construction of watermain on the Great Northern Nelson-Salmo Trail (GNT) began last week, with the crew working northward along the old rail bed from the top of Stanley Street toward the Mountain Station parking lot. Construction notices and detour signag...

Read on...

City Project Gallery
Posted on: May 11, 2020

Anderson Street Infrastructure Upgrade Update - May 11, 2020

Anderson Infrastructure Project

The underground infrastructure works are now complete for the Anderson Street Infrastructure Upgrade project. The water mains are in service and all of the service lines are connected.

Surface restoration works are underway, with concrete works scheduled t...

Read on...

City Project Gallery
Posted on: May 1, 2020

Anderson Street Infrastructure Upgrade Update - May 1, 2020

Anderson Infrastructure Project

Although it may not appear like it yet, the Anderson Street Infrastructure Upgrade project is nearing completion. Much of the water system upgrade work is now complete, with the numerous trench cuts marking either buried water main or buried water service...

Read on...

City Project Gallery
Posted on: April 28, 2020

Anderson Street Infrastructure Upgrade Update - April 28, 2020

Anderson Infrastructure Project

The infrastructure upgrade project along Anderson Street made significant strides last week, extending water main in both directions to the project commencement and termination points. The 200 and 300 blocks of Anderson Street, east of First Street were p...

Read on...

City Project Gallery
Posted on: April 17, 2020

Anderson Street Infrastructure Upgrade Update - April 17, 2020

Anderson Infrastructure Project

The City of Nelson and their prime contractor General Assembly Excavation Limited are currently working to install new water main on Anderson Street, near the intersection of Nelson Avenue. The milling of the pavement for the water main alignment is compl...

Read on...

City Project Gallery
Posted on: April 15, 2020

Anderson Street Infrastructure Upgrade Update - April 15, 2020

Anderson Infrastructure Project

The City of Nelson in conjunction with Ministry of Transportation and Infrastructure (MoTi) has an ambitious program of works scheduled for the Highway arterial through the City this construction season, culminating with a re-pave of the entire portion of...

Read on...

City Project Gallery
Posted on: March 25, 2020

Notice of Water Works & Paving Projects

Enhanced_WaterMain_edited

The following work will update the sections of old and undersized water lines to current standards:

  • Replacement of the main water line in the 700 to 900 blocks of Fourth Street.
  • Replacement of the main water line along 400 and 500 blocks of West Gore Street...
Read on...

City Project Gallery
Posted on: December 1, 2017

December 1, 2017 - UPDATE #10 - Hall Street Project - Phase II

10_HallStreetProgressUpdate

Click here to read the latest update on the Hall Street Project for the week of November 27th, 2017.

Read on...

City Project Gallery
Posted on: November 24, 2017

November 24, 2017 - UPDATE #9 - Hall Street Project - Phase II

9_HallStreetProgressUpdate

Click here to read the latest update on the Hall Street Project for the week of November 20th, 2017.

Placing Pipe during Phase II construction.

Read on...

City Project Gallery