August 5, 2022 - Update on Pier Project

22-07-05 - welding piles

Graham  Marine continued installing the pilings. They have now demobilized from the site, leaving one barge for the welder to continue work.

22-07-05 - welding piles

The site for the Ladybird display building was prepared and the concrete footings were placed.

22-07-05 - placing conc

The rebar and waterstop was completed for the walls of the Ladybird display building  and the concrete footing was backfilled.

22-07-28 - Backfill around walls

North Site view

22-07-29 - North site view

South Site view

22-07-29 - south site view